Construction project updates from across CHCCS

The CHCCS Maintenance Department has been busy working on multiple construction projects at many district schools over the summer, getting ready for students and staff to return in August.

Work continues on Elementary #11, which is being built to LEED Gold Specifications and will open in August 2013.

At Carrboro HS, construction of the physical education and athletic field's bathroom building is underway.  The building will accomodate restroom facilities, as well as be used during PE classes.

A new mobile unit has been added to Estes Hills Elementary to accomodate its new PreK class.  New HVAC units are also being installed in all of the school's lower nine classrooms to improve energy efficiency, control humidity and improve air quality.

The field lighting at Chapel Hill HS is being replaced at the school's stadium and soccer fields.  The old wood pole fixtures have been removed and new underground electrical service is being installed.  Lights are also being added to the softball field.

Roofs have been replaced at Glenwood Elementary, McDougle MS and Phillips MS.  Paving and parking lot repairs are being made at Seawell Elementary, Phillips MS and Chapel Hill HS.

Carrboro High's new bathroom building

Estes Hills Elementary being prepared for delivery of the mobile unit

Paving work at Phillips Middle School parking lot